Jackson (contractor) testing the pump that made construction possible |
Jackson, [the contractor] tried to explain that the
delay was the shortage of Cement in Ndola, that made even the Blocks not to be
made on time as he planned before. He said to the Committees that after we
finish filling the foundation next week Wednesday and Thursday especially if
the Community will come in a big number, then we can finish in two days time,
then the true estimation can now be as follows:
September - 0ctober
- November, the Construction shall be completed and December will be
final touches to made sure, its ready to be open in January 2015, when HealthEd
Connect will be here in January. What is needed is to be fully supported by the
Community and things will easier for us.
Isn't this great!!! The kids will have their little heads covered by real roofs before the rains come.